Project Environmental Factors

Project Environmental FactorsProject Environmental Factors

Consider a project to build a nuclear power plant in England in an area with high unemployment, but a large population.

Undertake a preliminary assessment of the project’s context.

Project Environmental Factors – Political

Is there government commitment to nuclear energy; if yes, then project in sound footing, if unclear then risk increased.

How does the local authority view the project – favourable then good news, against then more risk, and much more work to do on “hearts and minds”.

What sort of stakeholders will need to be considered in this area? Will they be positive or negative?

Project Environmental Factors – Economic

An area that has high unemployment may consider the relevance of grants, European funding, central government funding.

Likely to boost local jobs and economy so should engender positive views of local community.

Project Environmental Factors – Social

There is likely to be a mixed response.  Some people will see the investment providing jobs and boosting local economy whereas some may not want the threat of nuclear power in their area (closely linked to environmental considerations).

With the current security threat levels there are bound to be concerns in this area.  The project must consider the security implications, make the appropriate plans, and commit sufficient resource.

Project Environmental Factors – Technical

This will use new technology but there is expertise available.  The project will need to ensure proper representation from international suppliers who have the latest experience in this area.

The fact that the technology is new and is likely to change before the station is built indicates that the project budget must include for these possible changes and contain sufficient contingency to cater for unexpected problems.

Project Environmental Factors – Legal

There are likely to be legal challenges to the construction from a range of sources. It will be important to ensure that all areas are investigated and the appropriate legal team established to deal with challenges that are likely to be based on environmental concerns and local issues.  Consider any relevance of European legislation affecting nuclear installations.

Project Environmental Factors – Environmental

This is an area where there is likely to be the most concerns and where the majority of the opposition will come from.  There are likely to protest for anti-nuclear groups, environmental campaigners, and so forth.  The project will need to carefully research this aspect and ensure that appropriate security measures are put in place for people working on the project both in the planning and delivery phases.

Loved this? Spread the word


About the Author

David spent 25 years as a senior project manager for USA multinationals, and has deep experience in project management. He now develops a wide range of project-related downloadable video training products under the Primer and PM Mastery System brand names. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Dave

Related posts

Project Context

​Read More

Project Audit Smart List

​Read More

Project Management in Context

​Read More

Project Managers – PRINCE2 Practitioners and APM PMQ

​Read More
{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Subscribe to our newsletter now!